Yankee critics say documents found lacking

July 9, 2003

By SUSAN SMALLHEER Southern Vermont Bureau

BRATTLEBORO — Entergy Nuclear’s own experts believe that the proposed increase in power production at the Vermont Yankee nuclear power plant will accelerate the aging process at the 33-year-old reactor, a Washington , D.C. , expert on nuclear safety said Tuesday.

David Lochbaum, a nuclear safety engineer with the Union of Concerned Scientists, said that testimony submitted by Entergy’s own expert last week to the Vermont Public Service Board conceded that the so-called power uprate would age the plant even more.

Entergy Nuclear wants to increase power production at the plant by 20 percent, or 110 megawatts.

“The increased flows and temperatures will cause equipment to wear out quicker,” Lochbaum said. “Then it becomes a business decision.”

Entergy Nuclear has said it plans on spending at least $60 million on capital costs at the plant because of the power increase, but it has also estimated that it would make $20 million a year in increased profits.

At a press conference and a later public meeting, Lochbaum and nuclear experts who are working with the New England Coalition said their review of Entergy Nuclear documents in the past two days raised more questions than were answered.

Arnold Gundersen, a former nuclear industry executive turned whistleblower, said that the testimony submitted last week by Entergy’s expert, Edward Burns, predicted Vermont Yankee would be shut down on average an additional seven days a year because of problems from the power increase.

And those are seven days that Vermont utilities will have to scramble to pay for replacement power, Gundersen said.

Lochbaum, who worked as a nuclear engineer in the industry for 17 years before joining the national watchdog group, said that after looking at the documents, the good news was that Entergy engineers were raising good questions.

But the bad news, he said, is they don’t have the answers — at least not in the documents provided to the coalition as part of Entergy’s pending case before the Vermont Public Service Board.

“The problem had been identified, but the solution? I can’t say,” Lochbaum said.

“I would have expected to see more answers,” he said.

The New England Coalition held the press briefing and information session for about 45 people, including Sen. Mark MacDonald, D-Orange, and at least two members of the Brattleboro Select Board.

Greg Worden, chairman of the board, said he had questions about the uprate.

Lochbaum said the key cooling systems at the plant, which would be even more critical in the event of increased power production, hadn’t been analyzed for impact.

Likewise, that there were no studies of the effect of the increased steam and pressure on motor-operated valves in the plant was one example Lochbaum gave.

Raymond Shadis, a coalition staff member, had assembled a group of experts on various nuclear issues to help go over a raft of documents he had requested.

But the documents were in such disorder, lacking dates and, in some cases, missing hundreds of pages, the information was virtually impossible to use, Shadis said.

And Gundersen said it raised questions about whether Yankee was in compliance with its original design, as approved by the Nuclear Regulatory Commission.

Shadis said the New England Coalition last month had won an order from the PSB forcing Entergy to turn over the documents, and they were provided in largely unusable form.

As a result, Shadis said, a hearing officer from the Public Service Board will be at Entergy Nuclear’s corporate headquarters in Brattleboro first thing today to inspect the documents and to see if Entergy had complied with the board’s order.

Brian Cosgrove, Entergy Nuclear spokesman, said later Tuesday when contacted at home that he was unaware of the specifics of Burns’ testimony, but he expressed skepticism that he would have testified that the plant would on average shut down an additional seven days a year.

But he said that Entergy engineers had spent “hundreds of hours” assembling the requested documents. He estimated that between 15,000 to 20,000 pages of documents had been collected for the New England Coalition.

“We’ve made a tremendous effort for the intervenors,” he said.

As for the state inspection today, Cosgrove said Entergy welcomed the state hearing officer.

The Vermont Department of Public Service, which represents ratepayers in such cases, does not support the increased power production at this time, saying Entergy hasn’t proved that there’s a benefit to Vermont consumers.

Contact Susan Smallheer at susan.smallheer@rutlandherald.com.