|
Hearings
start on Yankee uprate
By SUSAN SMALLHEER Southern Vermont Bureau MONTPELIER — Members of the Vermont
Public Service Board questioned the head of Entergy Nuclear Vermont Yankee
Monday about whether there should be an independent analysis of his company’s
plan to increase power production by 20 percent, or 110 megawatts, at the
31-year-old reactor. And many of their questions seemed to come back to the lack of detailed
information about the $60 million-plus plan, and whether the increased power
production would make the plant more vulnerable to problems. The board at one time asked whether it should wait for the federal Nuclear
Regulatory Commission before it tackles the issues of economics and the
environmental effects of the project, which include the discharge of slightly
hotter water into the The review of the project is split between state and federal authorities,
with the federal regulators handling issues of safety and engineering. Entergy Nuclear has not submitted its NRC application yet, and won’t until
September, which will detail exactly how it plans to get more power out of the
510-megawatt Jay Thayer, site vice president at Entergy Nuclear, said the internal
temperature of the plant would increase significantly, and radiation levels
outside the plant would also increase, while at the same time remain within
state standards. “We expect an increase in the dose rate, but we still expect to be within
the 20 millirem (per year),” he said. The exact cost of the project remains a secret. Entergy Nuclear attorney
Victoria Brown objected to a question from Sarah Hofmann, the attorney for the
Department of Public Service, asking exactly how much the uprate would cost the
company. Brown said the cost wasn’t relevant, because the cost was being borne
entirely by Entergy. She also labeled the costs as proprietary information. The company had earlier this year estimated the capital costs of the project
at $60 million, but it became clear during the hearing that wasn’t the total
price. Thayer testified for most of the day, but several times he deferred answering
questions from either Chairman Michael Dworkin, board members David Coen or John
Burke, or parties to the case, or labeled the questions as “overly
simplistic.” Dworkin asked Thayer point-blank why Entergy wasn’t interested in an
outside opinion about the safety ramifications of putting additional pressure on
the internal components of the relatively old plant. “Why don’t you seek a peer review or an independent review? Why not ask
for an outside reality check?” Dworkin asked Thayer. Dworkin said the board had received many requests that the state ask for such
a review. Thayer said the Entergy Northeast nuclear “fleet,” which includes plants
in “We may come back to this question,” Dworkin said. Raymond Shadis, of the New England Coalition, an anti-nuclear group, asked
many of the questions. The Connecticut River Watershed Council and the Windham
Regional Commission also have concerns about the plan. Thayer admitted that the company was re-evaluating its long-term policy of
allowing enough storage capacity in its spent fuel pool that it could empty the
entire reactor of fuel in the event of an emergency. Thayer said Entergy Nuclear was thinking of changing its policy of leaving
space for a full core off-load, in order to free up more space for old fuel that
would be needed if the plant started producing more power. Lack of storage space for spent fuel could shorten the effective operating
life of the plant by 18 months, he said. Entergy Nuclear also announced Monday that it was changing one portion of the
plan that it had made public — that it wasn’t going to install
higher-powered fans in the cooling towers to help dissipate the additional heat
generated by the new power production. The plant had said it was going to install 200-horsepower fans at the top of
the towers, which are using in hot weather when the temperature of the One side effect of the smaller motors would be a larger steam plume coming
out of the cooling towers, he said The hearings continue today in Contact Susan Smallheer at susan.smallheer@rutlandherald.com. |